Old Dominion Freight Line
Greensboro, NC
| Architect: |
Hayes Howell |
| Sq. Feet: |
55,000 |
The 55,000 s.f. Old Dominion Freight Line terminal expansion on Bishop Road in Greensboro, NC, included the relocation of a state road crossing a Colonial Pipeline, removal of 90,936 cubic yards of rock, and construction of two retention ponds.
The existing terminal, office, and garage facilities were also renovated. Construction was completed in 11 months.
 |